Project Timeline

2012

Summer: Concept Plan submitted to provincial government.

2013

Business Plan development.

2014

Spring: Business plan submitted to provincial government.

July: Approval of business plan announced.

September: Release of Request for Qualifications (RFQ) seeking qualified companies to design, build, finance and maintain the patient care tower.

December: Announcement of RFQ short list.

Request for Proposals (RFP) to design, build, 2015finance and maintain the patient care tower.

 

2016

January: Preferred proponent selection.

July: Start of Patient Care Tower construction (Phase 1).

2017

March: Patient care tower named the David E. Kampe Tower after local businessman and philanthropist.

2019

Anticipated opening of the David E. Kampe Tower.

Renovations begin to expand the Emergency Department and support services (Phase 2).

2021

Phase 2 completion.

 